​​​​​​​​​December 3, 2019 


​The New High School, Middle School and Ag Building, New Elementary School, and Auditorium Renovations construction has progressed immensely in the past couple months and continues to develop.

Currently at the New High School, Middle School and Ag Building, progress is ongoing for the painting and installation of wall tile to the interior walls. The interior window glazing to the classrooms and offices are continuing to be installed. Also, installation is in progress for the ceiling grid and light fixtures throughout.

At the New Elementary School, the mechanical duct on the first and second floors are continuing to be installed and duct pressure tests are beginning. The erecting and detailing of the structural steel and metal stud walls are continuing to be installed.

The Auditorium’s control booth installation is in progress. Drywall, tape and float is almost near completion. The interior metal stud framing, and plumbing riser are being installed in the men and women’s restrooms.

The team continues to work diligently to provide the best for our community and we greatly appreciate all who have been a part of this wonderful development.

April 2, 2019 


We started the year off with the Groundbreaking Ceremony for the New High School, Middle School and Ag Building. 


As construction began, we experienced a considerable amount of rain causing the site to be very wet. The team continued working with select fill to build up the building pad, installing underground water mains, drilling and pouring concrete for piers.


This past Tuesday, March 26th, we held the Groundbreaking Ceremony for the New Elementary School. Currently, the slab has been poured and completed in certain areas; plumbers and electricians are continuing to install underslab plumbing and conduit on the south end of the site.


We appreciate all who have been and will continue to be a part of such an exciting time for our community.


We look forward to providing regular updates on this site regarding construction progress.


​​​​​​October 1, 2019 


The construction is ongoing and the development of each project has progressed tremendously for the New High School, Middle School and Ag Building, New Elementary School and Auditorium.


The New High School, Middle School and Ag Building currently has ongoing roof installation, windowinstallation, and waterproofing throughout. The brick masons have started installing brick on the exterior walls. Also tile installation, ceiling grid is being installed in classrooms and office. 


​At the New Elementary School, steel and metal decking installation is ongoing, as well as the hangers and straps are being installed. Block outs around columns have been poured back. 


Also the Auditorium has ongoing metal stud framing. Overhead duct is currently being installed. Old door frames around the stage area are being replaced for new door frames.

 

The team is working hard to provide the best of the best for our community and we appreciate all who has been a part of the growth and development of our schools.


We look forward to providing month to month updates on this site regarding the progress of the current construction.  